Wednesday, April 19, 2006

Status of PLs Proposed Bear River Old-Growth Logging Plans



The following was modified from a CDF Timber Harvest Plan Status Report sorry about all the acronyms. It seems like I'm up to my neck in logging plans right now and its a little difficult to keep up with all of them. The Old Growth Redwood logging plans in Elk River will be featured soon.

1-05-237 (PC Road)
PHI held on 4/4/06. Received CDF PHI (pre-harvest inspection) report on 4/5/06. Need Californa Geological Survey PHI report Submitted as a HCP Option “A” THP utilizing the Interim Watershed Prescriptions (Bear River). Going to second review tomorrow, public comment period could close in 10 days.

1-06-001 (Brush Up)
Received PLs response to PHI recommendations on 3/27/06. Recommended for approval WITHOUT additional mitigation (A). Public comment period to close on 4/10/06 (PHI held on 3/8/06). Submitted as a HCP Option “A” THP utilizing the HCP Interim Watershed Prescriptions.
Tenative approval decision date- 5/1/06
Public comment closed.


1-06-036 (Mas Patron)
Filed 4/6/06. Pending scheduling of PHI. Submitted as a HCP Option “A” THP utilizing the Interim Watershed Prescriptions.
Still open for comment.

1-06-037 (Rock/Chadbourne)
RETURNED (due to some unidentified flaw in the plan)